In 2025, Romania generated 49.8 TWh of electricity and used 54.4 TWh. Hydro was the largest source at 24% of generation.
251gCO₂/kWh grid intensity#19 of 30 · EU 210
68%low-carbon electricityEU 71%
0.160€/kWh industrial, 2026 H1#22 cheapest · EU 0.135
130€m/yr power for 100 MW AI campus220 kt CO₂/yr
68% of its electricity came from low-carbon sources (nuclear and renewables), below the EU-27 average of 71%. Grid carbon intensity was 251 gCO₂/kWh, ranking #19 of 30 European countries (1 = cleanest), down 32% since 2015. Industrial users consuming 20–70 GWh a year paid €0.160/kWhexcluding VAT in 2026 H1, more than the EU-27 average of €0.135 (#22 cheapest of 28). At €0.148/kWh, a 100 MWAI data center running at full load (876 GWh a year) would pay about €130 million a year for electricity and, on the average grid mix, be responsible for about 220 kt of CO₂.
Electricity generation mix, 2025
Source
Romania
EU-27
Nuclear
20.5%
23.3%
Hydro
24.3%
11.7%
Wind
12.0%
17.1%
Solar
9.8%
13.1%
Bio & other renewables
1.0%
5.8%
Gas
18.7%
16.7%
Coal
13.4%
9.2%
Oil
0.4%
3.1%
Grid carbon intensity, 2005–2025
gCO₂ per kWh of electricity generated. Lower is cleaner.
Wind and solar share of generation
Industrial electricity price, 2019–2026 H1
Non-household consumers using 20–70 GWh/yr, excluding VAT and recoverable taxes, €/kWh.
Infrastructure & market
45colocation facilities (PeeringDB)
20data centers mapped in OpenStreetMap
–HV substations (pending)
3,807MW cross-border capacity, 2030 grid (TYNDP)
–wholesale price (no single zone)
–negative-price hours
165cooling degree days (5-yr avg)
1,106kWh/kWp solar yield at the capital (PVGIS)
Romania has 45 colocation facilities listed in PeeringDB, and hosts 1 EuroHPC AI Factory (RO AI Factory). The TYNDP 2030 starting grid gives it about 3,807 MW of cross-border transmission capacity. Its climate averaged 165 cooling degree days a year (Eurostat), a rough guide to how hard data center cooling has to work.