In 2025, France generated 570.0 TWh of electricity and used 476.7 TWh. Nuclear was the largest source at 69% of generation.
41gCO₂/kWh grid intensity#4 of 30 · EU 210
95%low-carbon electricityEU 71%
0.098€/kWh industrial, 2026 H1#5 cheapest · EU 0.135
70€m/yr power for 100 MW AI campus36 kt CO₂/yr
Grid access outlook (editorial)More room
Nuclear baseload, fast-track sites
95% of its electricity came from low-carbon sources (nuclear and renewables), above the EU-27 average of 71%. Grid carbon intensity was 41 gCO₂/kWh, ranking #4 of 30 European countries (1 = cleanest), down 30% since 2015. Industrial users consuming 20–70 GWh a year paid €0.098/kWhexcluding VAT in 2026 H1, less than the EU-27 average of €0.135 (#5 cheapest of 28). At €0.079/kWh, a 100 MWAI data center running at full load (876 GWh a year) would pay about €70 million a year for electricity and, on the average grid mix, be responsible for about 36 kt of CO₂.
Electricity generation mix, 2025
Source
France
EU-27
Nuclear
68.8%
23.3%
Hydro
10.4%
11.7%
Wind
8.2%
17.1%
Solar
5.6%
13.1%
Bio & other renewables
1.9%
5.8%
Gas
3.0%
16.7%
Coal
0.3%
9.2%
Oil
1.8%
3.1%
Grid carbon intensity, 2005–2025
gCO₂ per kWh of electricity generated. Lower is cleaner.
Wind and solar share of generation
Industrial electricity price, 2019–2026 H1
Non-household consumers using 20–70 GWh/yr, excluding VAT and recoverable taxes, €/kWh.
Infrastructure & market
227colocation facilities (PeeringDB)
235data centers mapped in OpenStreetMap
–HV substations (pending)
29,915MW cross-border capacity, 2030 grid (TYNDP)
94€/MWh avg wholesale price, last 12 months
536hours with negative prices, last 12 months
79cooling degree days (5-yr avg)
957kWh/kWp solar yield at the capital (PVGIS)
France has 227 colocation facilities listed in PeeringDB, and hosts 1 EuroHPC AI Factory (AI Factory France). Over the last 12 months the average day-ahead wholesale price was €94/MWh, with 536 hours of negative prices. The TYNDP 2030 starting grid gives it about 29,915 MW of cross-border transmission capacity. Its climate averaged 79 cooling degree days a year (Eurostat), a rough guide to how hard data center cooling has to work.