 "campuses": [
  {
   "name": "Stargate Norway",
   "country": "norway",
   "city": "Narvik",
   "lat": 68.44,
   "lon": 17.43,
   "precision": "site",
   "developer": "Nscale & Aker (JV), OpenAI as offtaker",
   "mw_initial": 230,
   "mw_max": 520,
   "gpus": "100,000 NVIDIA GPUs targeted by end of 2026",
   "status": "announced",
   "year_announced": 2025,
   "target": "2026",
   "power": "Renewable (hydro)",
   "note": "230 MW initial, ambition to add 290 MW.",
   "source": "https://www.nscale.com/press-releases/stargate-norway-nscale-aker-openai",
   "source_type": "primary"
  },
  {
   "name": "Fluidstack AI supercomputer, France",
   "country": "france",
   "city": "France (site not disclosed)",
   "lat": 48.86,
   "lon": 2.35,
   "precision": "approx",
   "developer": "Fluidstack (MoU with French government)",
   "mw_initial": 1000,
   "mw_max": null,
   "gpus": "~500,000 next-generation chips in phase 1",
   "status": "mou",
   "year_announced": 2025,
   "target": "Phase 1 from 2026, beyond 1 GW by 2028",
   "power": "Predominantly nuclear",
   "note": "€10bn initial investment.",
   "source": "https://www.fluidstack.io/post/1gw-ai-supercomputer-france",
   "source_type": "primary"
  },
  {
   "name": "Mistral AI × EcoDataCenter",
   "country": "sweden",
   "city": "Borlänge",
   "lat": 60.49,
   "lon": 15.44,
   "precision": "site",
   "developer": "EcoDataCenter, Mistral AI",
   "mw_initial": 250,
   "mw_max": 600,
   "gpus": "NVIDIA Vera Rubin",
   "status": "announced",
   "year_announced": 2026,
   "target": "2027",
   "power": "Swedish grid (low-carbon)",
   "note": "€1.2bn; Mistral's first AI infrastructure outside France.",
   "source": "https://www.datacenterdynamics.com/en/news/french-ai-firm-mistral-signs-12bn-deal-to-lease-ecodatacenter-facility-in-sweden/",
   "source_type": "secondary"
  },
  {
   "name": "Start Campus Sines (Nscale for Microsoft)",
   "country": "portugal",
   "city": "Sines",
   "lat": 37.95,
   "lon": -8.87,
   "precision": "site",
   "developer": "Start Campus; Nscale for Microsoft",
   "mw_initial": 200,
   "mw_max": 1200,
   "gpus": "12,600+ Blackwell Ultra (SIN01); 66,000+ Rubin from late 2027",
   "status": "partly-live",
   "year_announced": 2025,
   "target": "Late 2027 (second building)",
   "power": "Grid + renewables",
   "note": "Campus permitted for 1.2 GW; €465m for a second 200 MW building.",
   "source": "https://www.nscale.com/press-releases/nscale-start-campus",
   "source_type": "primary"
  },
  {
   "name": "Nscale Loughton",
   "country": "united-kingdom",
   "city": "Loughton, Essex",
   "lat": 51.65,
   "lon": 0.07,
   "precision": "site",
   "developer": "Nscale",
   "mw_initial": 50,
   "mw_max": 90,
   "gpus": "23,040 GPUs planned for Azure",
   "status": "delayed",
   "year_announced": 2025,
   "target": "Was Q4 2026; grid power now expected in the 2030s",
   "power": "Grid (delayed)",
   "note": "Microsoft reported to have withdrawn (Oct 2026); Nscale exploring alternative power.",
   "source": "https://datacenterdynamics.com/en/news/microsoft-pulls-out-of-delayed-nscale-data-center-in-loughton-essex",
   "source_type": "secondary"
  },
  {
   "name": "Mistral training cluster (Eclairion)",
   "country": "france",
   "city": "Essonne",
   "lat": 48.59,
   "lon": 2.19,
   "precision": "site",
   "developer": "Eclairion, Fluidstack, Mistral AI",
   "mw_initial": null,
   "mw_max": null,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": null,
   "power": "French grid (nuclear)",
   "note": "Multi-year hosting deal for Mistral's training cluster.",
   "source": "https://datacenterdynamics.com/en/news/gpu-cloud-provider-fluidstack-signs-mou-for-1gw-ai-supercomputer-in-france",
   "source_type": "secondary"
  },
  {
   "name": "Azora / Tillion data campus",
   "country": "spain",
   "city": "Villamayor de Gállego, Zaragoza",
   "lat": 41.68,
   "lon": -0.77,
   "precision": "site",
   "developer": "Azora, Tillion",
   "mw_initial": null,
   "mw_max": 300,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": null,
   "power": null,
   "note": "Initial €1.1bn, up to €2bn.",
   "source": "https://blackridgeresearch.com/blog/largest-latest-top-upcoming-data-centers-in-europe-list",
   "source_type": "secondary"
  },
  {
   "name": "Microsoft Zaragoza campus",
   "country": "spain",
   "city": "Aragón",
   "lat": 41.65,
   "lon": -0.88,
   "precision": "approx",
   "developer": "Microsoft",
   "mw_initial": null,
   "mw_max": null,
   "gpus": null,
   "status": "announced",
   "year_announced": null,
   "target": "Construction from 2026",
   "power": null,
   "note": "About $3.4bn; capacity not disclosed.",
   "source": "https://blackridgeresearch.com/blog/largest-latest-top-upcoming-data-centers-in-europe-list",
   "source_type": "secondary"
  },
  {
   "name": "DC Malpica AI campus",
   "country": "spain",
   "city": "Mora, Toledo",
   "lat": 39.68,
   "lon": -3.77,
   "precision": "site",
   "developer": "DC Malpica",
   "mw_initial": null,
   "mw_max": 300,
   "gpus": null,
   "status": "announced",
   "year_announced": 2026,
   "target": null,
   "power": null,
   "note": "Announced July 2026.",
   "source": "https://cloudnews.tech/europes-data-center-boom-over-3-2-gw-announced-in-a-single-month/",
   "source_type": "secondary"
  },
  {
   "name": "Apto Lacchiarella campus",
   "country": "italy",
   "city": "Lacchiarella, Milan",
   "lat": 45.32,
   "lon": 9.14,
   "precision": "site",
   "developer": "Apto",
   "mw_initial": null,
   "mw_max": 300,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": null,
   "power": null,
   "note": "About $3.4bn.",
   "source": "https://blackridgeresearch.com/blog/largest-latest-top-upcoming-data-centers-in-europe-list",
   "source_type": "secondary"
  },
  {
   "name": "EdgeConneX Lombardy campuses",
   "country": "italy",
   "city": "Lombardy",
   "lat": 45.46,
   "lon": 9.19,
   "precision": "approx",
   "developer": "EdgeConneX",
   "mw_initial": null,
   "mw_max": 300,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": "2031",
   "power": null,
   "note": "€3bn across three campuses, total above 300 MW.",
   "source": "https://blackridgeresearch.com/blog/largest-latest-top-upcoming-data-centers-in-europe-list",
   "source_type": "secondary"
  },
  {
   "name": "QTS Vimercate",
   "country": "italy",
   "city": "Vimercate, Milan",
   "lat": 45.61,
   "lon": 9.37,
   "precision": "site",
   "developer": "QTS Data Centers",
   "mw_initial": null,
   "mw_max": 220,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": null,
   "power": null,
   "note": "Up to €2.3bn.",
   "source": "https://blackridgeresearch.com/blog/largest-latest-top-upcoming-data-centers-in-europe-list",
   "source_type": "secondary"
  }
 ]
}